The City of Keene Public Works Department announces the following construction and maintenance activities scheduled for the week of November 22, 2026. Motorists, pedestrians, and cyclists are encouraged to use caution when traveling through active work zones, follow posted signage, and expect minor delays.
Central Square: On Monday, November 23rd, the City’s contractor Casella Construction, Inc will continue construction operations to sewer utilities in Central Square and Main Street in proximity to Davis Street. In order to safely perform this work parking spaces and sections of Central Square that are engaged in active construction will be shifted and/or closed and detoured. Traffic operations and parking will be restored to normal operating conditions by the end of each business day. Please refer to the Downtown Construction press release for a more detailed summary of construction activities and closures.
George Street Bridge: On Monday, November 23rd , the City’s contractor New England Infrastructure, Inc. will be performing site cleanup and completing the installation of the gabion wall along the stream bank. George Street and the bridge will be re-opened to traffic on Wednesday November 25th . The construction site cleanup is anticipated to be completed on December 6th for the shutdown of the construction season. The final paving, vegetation restoration and sidewalk installation planned for the spring of 2027 to complete the project.
Elm Street: On Monday, November 23rd at 8:00 AM Gordon’s Property Maintenance Services will be continuing to install a new water main on Elm Street between Timberlane Drive and Drummer Hill Road. In order to safely perform this work traffic in the area(s) of active construction will be established as alternating one way as appropriate during construction. This work is anticipated to continue thru Wednesday November 25th , and traffic is planned to be restored to normal operations by the end of the day.
Maple Avenue: Starting on Wednesday, November 25th at 8:00 AM the City’s contractor Phil’s Tree Service will be clearing trees on Maple Avenue along Wheelock Park. In order to safely perform this work, Maple Ave will be closed and detoured. This work is anticipated to take the day to complete , and traffic is planned to be restored to normal operations by the end of the day.
Monadnock View Cemetery (Park Ave): Starting on Monday, November 23rd at 7:00 AM the City’s contractor Park Construction, Corp. will be starting construction of the Monadnock View Cemetery Expansion Project. In order to safely perform the work the sections of the cemetery under active construction will be closed to the public both during construction and after hours. This work is anticipated to continue thru Wednesday November 25th for the week, and construction activities will be completed at the end of each business day.
Robin Hood Park Pool (Reservoir St): On Monday, November 23rd at 9:00 AM the City’s contractor Weston & Sampson CMR will be working on the installation of drains for the Pool rehabilitation at Robin Hood Park in order to safely perform this work access to the areas of active construction and to the staging areas in the parking lot will be closed to the public. This work is anticipated to continue through Wednesday November 25th , and access will remain closed for the pool and parking lot area until the project is completed.
The City of Keene appreciates the public’s patience and cooperation during these projects. For the safety of workers and the traveling public, please slow down, follow all posted traffic control devices, and use caution when traveling through construction areas.