Good afternoon,
Casella Construction, Inc. made steady progress on downtown utility upgrades last week. Crews connected the new Central Square water main to the existing system at Washington Street and Roxbury Street and completed service connections on the east side of the Square. Crews also continued sewer main improvements at the Roxbury Street intersection, working north toward Washington Street.
Planned Work Activities
- Monday, November 23–Wednesday, November 25: Crews will continue underground utility upgrades, installing new sewer pipe and structures from the Roxbury Street intersection north toward Washington Street. Crews will also begin sewer upgrades on West Street heading into Central Square.
- Thursday, November 26 (Thanksgiving)–Friday, November 27: There will be no crews working for the long holiday weekend.
- Monday, November 30—Friday, December 4: Crews will continue sewer upgrades from Roxbury Street to Washington Street, as well as on West Street at Central Square.
- Monday, November 30—Friday, December 4: Crews will begin installing new sewer pipe and structures at the Davis Street intersection, working south toward Water Street.
Parking Impacts
Monday, November 23 – Wednesday, November 25 & Monday, November 30—Friday, December 4:
- Parking Closures: Several parking spaces on the north, east, and west sides of Central Square will be closed from 7:00 AM until the end of each workday.
- No Parking Zones: Any parking spaces blocked by orange cones or barriers are designated as No Parking zones.
- Alternative Parking: Multiple public parking lots within a short walking distance remain open and available. For parking locations and additional information, please visit the City’s Parking Services webpage.
Traffic Impacts & Detours
Monday, November 23—Wednesday, November 25:
- Roxbury Street Closure: The Roxbury Street/Central Square Intersection will remain closed. Traffic traveling from Roxbury Street toward Central Square will be detoured via Franklin Street → Beaver Street.
- West Street Closure: Eastbound traffic heading into Central Square will be detoured via West Street to School Street → Gilbo Avenue. Traffic heading through Central Square toward West Street will be detoured via Gilbo Avenue → School Street.
Monday, November 30—Friday, December 4:
- West Street Closure: Eastbound traffic heading into Central Square will be detoured via West Street to School Street → Gilbo Avenue. Traffic heading through Central Square toward West Street will be detoured via Gilbo Avenue → School Street.
- Davis Street Closure: Davis Street will be closed at Main Street with detours in place via Winchester, Wilson, and Emerald Streets. Local access from Wilson Street will be maintained.
- Main Street Lane Closure: The right lane on southbound Main Street will be closed at Davis Street.
- Main Street Lane Shifts: Throughout the week, temporary lane shifts and lane closures will be in effect on both the northbound and southbound sides of Main Street, from Water Street to Central Square.
Stay Alert: Construction activities and traffic impacts may shift as work progresses. Motorists and pedestrians should use caution, stay alert, and expect changing traffic patterns throughout the project area. Normal traffic and parking operations will resume at the end of each workday.
Thank you for your continued support. If you have questions, please contact our Downtown Project Ombudsman, George Downing, at (603) 757-2105 or gdowning@keenenh.gov, or contact me directly at (603) 352-6550.
Bill Siemer, P.E.
Assistant City Engineer