Good afternoon,
Casella Construction, Inc. continued making progress on downtown utility upgrades this past week. Crews advanced sewer main improvements at the Roxbury Street intersection and completed exploratory excavations in the southern portion of the project area to locate existing water, sewer, and drainage utilities and service connections. The newly installed water mains around Central Square were also disinfected, flushed, and tested to verify water quality and confirm the absence of bacteria.
Planned Work Activities
- Monday, November 9–Friday, November 13: Underground utility improvements will continue. Casella will install new sewer pipe and structures from the Roxbury Street intersection north toward Washington Street. Crews also plan to complete final water main connections to buildings around Central Square. In addition, installation of new sewer pipe and structures will begin along Davis Street.
- Monday, November 9–Thursday, November 12: Liberty Utilities crews will replace gas service connections along Main Street between Water Street and Davis Street.
Parking Impacts
Monday, November 9–Friday, November 13:
- Parking Closures: Several parking spaces on the north, east, and west sides of Central Square will be closed beginning at 7:00 AM and remain closed until the end of each workday.
- No Parking Zones: Any parking spaces blocked by orange cones or barriers are designated as No Parking zones.
- Alternative Parking: Several public parking lots within a short walking distance remain open and available. For parking locations and additional information, visit the City’s Parking Services webpage.
Traffic Impacts & Detours
Monday, November 9–Friday, November 13:
- Roxbury Street Closure: The Roxbury Street/Central Square intersection will remain closed. Traffic traveling from Roxbury Street toward Central Square will be detoured via Franklin Street and Beaver Street.
- Main Street Lane Shifts: Temporary lane shifts and closures will be in effect throughout the week on both the northbound and southbound sides of Main Street, between Water Street and Central Square.
- Stay Alert: Construction activities and associated traffic impacts may change as work progresses. Motorists and pedestrians are encouraged to use caution, remain alert, and be prepared for changing traffic patterns throughout the project area.
- Daily Restoration: Traffic operations and parking will return to normal conditions by the end of each workday.
Other News
- Coffee & Hardhats: Keene Public Works will host its monthly Coffee & Hardhats meeting for the Downtown Infrastructure Project on Tuesday, November 10, at 9:00 AM at the Transportation Center, located at 12 Gilbo Avenue. The public is invited to attend, ask questions, and learn more about the project. Those unable to attend can sign up for email updates and visit the City’s website for project information and updates.
- Veterans Day Work Schedule: Although the City will observe Veterans Day on Wednesday, November 11, Casella Construction, Inc. will maintain its regular work schedule and operating hours.
Thank you for your continued support. If you have questions, please contact our Downtown Project Ombudsman, George Downing, at (603) 757-2105 or gdowning@keenenh.gov, or contact me directly at (603) 352-6550.
Bill Siemer, P.E.
Assistant City Engineer