Keene Dillant-Hopkins Airport (EEN) Reconstruct Taxiway ‘A’ (3,500’ x 35’) Reconstruct Taxiway ‘A3’ (440’ x 35’) and Reconstruct Taxiway ‘T’ (250’ x 25’) Project Update #12

Keene Dillant-Hopkins Airport (EEN) is working on a taxiway reconstruction project on the airfield for taxiways ‘A’, A3’ and ‘T’. The existing pavement has served its design life and is being reconstructed. The Scope of Work items will include but not be limited to erosion control, demolition, lighting, storm drainage, grading, paving, and marking and turf restoration for disturbed areas.


Project Update: Construction resumed Monday April 20, 2026 and is tentatively scheduled to complete on Friday June 5, 2026. This is a period of 47 days. During this time there will be periods of time that portions of TXY A as well as TXY C and TXY T will be closed. There will be days when daily closures happen to runways, but not both runways at the same time. NOTAMS will be issued in advance and Project Status Updates will be issued.


This week we successfully completed scheduled work on TXY A between TXY T and TXY A2 as well as on TXY C. TXY C is now TXY A3 on the signs. We are in process of getting related documents updated to TXY A3. As of 5 pm today TXY A3 and TXY A between TXY A2 and TXY A3 will reopen for use. Also this week we began reconstruction of TXY T and TXY A between TXY T and RWY 14/32. This work is on schedule.


Upcoming Impacts: TXY T and the T-Hangar Ramp remain closed 24 hours a day, at this point we are still on schedule to reopen those on Friday 5/22/26.

  • Friday 5/1/26 through Friday 5/22/26 Taxiway A between Runway 14/32 and Taxiway A3
    closed.
  • Monday 4/27/26 through Friday 5/22/26 Taxiway T closed. During this time there will be no way to get a plane in or out of the T-Hangar area.
  • Beginning Tuesday 5/12/26 and Friday 5/22/26 there will be daily closures of RWY 14/32 as needed to perform work within the RWY 14/32 safety area.

Keene Airport staff, our engineering team and the contractor are committed to ensuring that the work proceeds efficiently and safely. We all aim to reduce impacts to tenants and users of the Airport as much as is possible