Gilbo Ave To Railroad St Intersection Banner Photo

Downtown Project

Downtown Infrastructure Project Information

Current Phase: Final Design

In July of 2023, the City Council adopted the "Multilane Hybrid" conceptual design for the Downtown Infrastructure Improvement Project. The Preliminary Design (see presentation slides) was then created (and approved by the City Council in July 2024) using the Multilane Hybrid concept to develop the detailed plans and specifications required for construction.  The approved preliminary design was used to conduct a thorough infrastructure technical analysis that informed the final design that was presented to the City Council's MSFI committee on December 18th, 2024. 

Detailed background information is posted online on the consultant's website, including utility infrastructure analysis, design concepts, full presentations, traffic and pedestrian analyses, tree study findings, and more.  Use the links at the top of this page to view detailed background information for each of the concepts and designs.

The Keene Downtown area is the economic engine for the community and represents the spirit and place of Keene. It is critically important to continue investment in the Downtown to support local businesses and the broader community and keep the area relevant and vibrant.  Much of Keene's downtown underground infrastructure has aged beyond its useful life including water, sanitary sewer, stormwater, electrical, telecommunication and gas - some of which date back to over 120 years. The last major downtown revitalization occurred in 1988. The need for utility improvements is critical and is now a top priority.  (View the 1884 survey of the Central Square water system.)

Contact:
Keene Public Works, (603) 352-6550
Contact Us

Meetings and Updates

Next Steps

Final Design Recommendation
On December 18th, 2024, City staff reviewed the final project design at the City Council's MSFI Committee public meeting.  The final design considers the project features and elements and is the product of a thorough infrastructure technical analysis that commenced upon City Council's approval of the preliminary design.  Following approval of the final design, construction for phase one (Central Square) is scheduled to begin in May 2025.

The final design presentation included a review of options for elements such as:  Sidewalk materials, bike lane delineations, raised crosswalk materials, bicycle racks, trash receptacles, hydrant styles, planting bed styles, surface treatments around trees, street lights, power pedestals, light bollards, catenary light styles, leaning rails, Railroad Square surface materials and shade structure, Railroad Square track motif, gateway arch design, Central Square path materials, and bench styles.

The design team also reviewed the project Phasing Plan and traffic control plans including work restrictions such as number of parking spaces to be taken out of service to accommodate the work, work hours, utility disruptions, etc.  Methods planned to support downtown residents and businesses were reviewed including a project ombudsman, monthly MSFI Committee updates, monthly "coffee and hardhats" meetings, use of variable message boards for advance notifications, weekly project update email, and accommodations for downtown events.

The MSFI Final Design recommendation will be sent to the City Council for approval, and the consultant will then prepare the bid documents to be advertised for construction.  The project will then be advertised in March of 2025 with bid opening to take place in April of 2025.  Construction is expected to begin in May of 2025.

MSFI Meetings

  March 13, 2024, 5:30 PM, Focus Area: Main Street Streetscape
Presentation Slides
  April 24, 2024, 5:30 PM, Focus Area: Gilbo Avenue/Railroad Square
Presentation Slides
  May 8, 2024, 5:30 PM, Focus Area: Central Square
Presentation Slides
  May 22, 2024, 6:00 PM
Presentation Slides
  June 11, 2024, 7:00 PM
Presentation Slides
  June 26, 2024, 6:00 PM
Presentation Slides
  December 18, 2024 6:00 PM Final Design Review
Presentation Slides

A Council Workshop took place June 11th, 2024.  The City Council reviewed the draft preliminary design plan, as it has been developed and refined through a series of public workshops and MSFI project update meetings.  Councilors reviewed the complete project scope and provided input to the design team.
Presentation Slides

Public Workshops - Complete (March, April, and May, 2024)

11/5/2024 Project Update

1/19/2024 Project Update